Projects.


Amharc has earned an enviable reputation for structural concreting excellence on the back the delivery of numerous high quality projects. Our customer-focused approach is fundamental to our success on the following projects:

Amharc Projects

Upcoming Work

  • Project: Walkerston Bypass

Case Studies

Amharc’s project management and field staff have been involved with the delivery of a number of highly successful civil infrastructure projects including;

CASE STUDY 1:

Burnett River Bridge, QLD

In August 2016, Amharc Pty Ltd was awarded the structures package for the Burnett River Bridge Replacement project on the Monto-Mt Perry Road near Monto, Queensland. The package was awarded by the principal contractor, Doval Constructions. This project is due to commence in late September or early October and will include the construction of a 5 span bridge over the Burnett River and numerous culverts. Expected project duration is 4 months.


CASE STUDY 2:

Oxley Sewage Treatment Plant Stage 1-4, Oxley, QLD

Initially engaged on a lump sum contract to construct 4 new concrete baffle walls, Amharc successfully secured additional works on the project following the successful execution of the originally contracted works. These additional works included concrete skylight, stopboard and weir FRP infills and construction of a new flowmeter pit. Amharc also provided labour hire services on Oxley STP providing pipelayers, labourers, formworkers, steelfixers and concreters. During their time on site Amharc personnel showed a continued commitment to improving safety and carried out their works to a high standard of quality evidenced by the fact that no NCR’s were issued throughout our 9 months on site.


CASE STUDY 3:

Warrego Highway Upgrade, Charlton, QLD

Amharc was contracted by Georgiou Group to deliver a two span bridge across the Warrego Highway at Kingsthorpe along with baseslabs, apron slabs and headwalls/wingwalls for 54 culverts and gas protection works for an existing gas main running through the site. These works were carried out to a strict programme to enable the clients traffic switches to happen as planned. The project commenced in April 2017 and was completed within 10 months having a peak workforce of 18 men.


CASE STUDY 4:

Road Maintenance Crews

Amharc are working with Roadtek on an ongoing basis on various road maintenance works through South East Queensland. These works include but are not limited to sound barrier repairs on all major arterials, installation and replacement of tactiles, fence and gate repairs, removal of graffiti, painting, installation of concrete footpaths, medians, pram ramps, etc.


CASE STUDY 5:

Mango Hill Park & Ride

Ertech engaged Amharc to the Construction of FRP works on the Mango Hill Park n’ Ride upgrade. These include 4 sets of retaining walls with Storm water penetrations and drainage holes. In total the project involves the placement of 400m3 of concrete and fixing of 120t of steel.


CASE STUDY 6:

Arnwood Place Shared Path

Amharc were engaged by Roadtek to construct stage 2 of the Arnwood Place shared pathway in Annerley, QLD. This involved the supply and installation of 300m3 of concrete. The works also involved the construction of a pipe culvert apron and headwall as well as scour protection works on the adjacent embankment. On the back of our successful completion of the works on time, we have been given the opportunity to build on our relationship with Roadtek with numerous other contracts awarded to us.


CASE STUDY 7:

Rockhampton to Gracemere Duplication

Amharc were engaged by Fulton Hogan to carry out the FRP works on the Rockhampton to Gracemere Duplication Project. This involves construction of one road bridge and one pedestrian bridge over Scrubby Creek and the construction of 34 culverts including FRP of base slabs, aprons, headwalls, wingwalls, placement of RCBC units, sealing and filling between units with lean mix concrete. Works also included batter protection slabs, gas protection works, water main protection slabs, footpaths, driveways, median strips and drainage channels.


CASE STUDY 8:

Lowood Sewer Pump Station

Amharc were engaged by Ventia to contract a 9m deep 4m diameter wet well and other infrastructure for Lowood Sewer pump station including a grit chamber, diversion chamber, maintenance holes and generator footings. The works needed to be carried out to a tight timeline within an active Wastewater Treatment plant without any disruptions to the plant operations. A mechanically anchored polyethylene liner was cast into the internal face of all structures to prevent concrete degradation ordinarily caused by hydrogen sulphide in the wastewater.


CASE STUDY 9:

Kawana Treatment Plant

Monadelphous engaged Amharc to supply men to construct the new MBBR tank, PST inlet works and some other smaller structures within the existing Kawana Treatment Plant. The brownfield project commenced in September 2017 and is due for completion in mid 2018. Peak workforce on the project was 16 men.


CASE STUDY 10:

Canberra Light Rail

Canberra Metro (a John Holland and CPB Joint Venture) engaged Amharc to supply grouters to supplement their rail installation crew on site. The crew was responsible for installing and grouting the new rails into recesses cast into the slip formed pavement for the new tramway within the Canberra urban area.


CASE STUDY 11:

Logan Enhancement Project

Amharc were engaged by CPB to construct 2 no. new overpasses in 3 stages and 2 no. 8 span bridge widenings. This work formed the scope of BR03 and BR04 on the Logan Enhancement Project, a $512m upgrade of the Logan Motorway and Gateway Extension Motorway for Transurban Queensland. The project commenced in November 2017 with an expected duration of 12 months. Peak workforce on site is expected to be 20.


CASE STUDY 12:

Kangaroo Point Bikeway Stage 1A and 1B

Amharc were engaged by Pensar to construct numerous concrete retaining walls between 400mm high and 5m high and to form and pour over 2000m2 of concrete footpaths, bikeways, driveways and pram ramps. The project was logistically complex and site restraints led to extremely tight work fronts with limited working room and a high degree of pedestrian/cyclist/vehicle traffic around the work site. Amharc maintained a strong commitment to safety, and their expertise and efforts in completion of the package of works was a key component to the overall successful completion of the Stage 1A project on time. Amharc’s performance on the Stage 1A works led to the award of the subsequent concrete package of works for Stage 1B


CASE STUDY 13:

Maryborough Rail Facility

Amharc were engaged by CMC to carry out construction of reinforced concrete track slabs for both straight and curved rail sections as part of an expansion to Downers stabling yard in Maryborough. Works also included construction of a 3-way turnout, rail tie-ins to existing rail infrastructure and the construction of 3 maintenance pits to existing and new rail tracks. Installation of and setting of the rail to very fine tolerances utilising a Trelleborg bracket system to secure the rail prior to pouring of the concrete required the utmost diligence and attention to detail from our skilled workforce. The project was completed on schedule and with no safety incidents.


CASE STUDY 14:

Cross River Rail

Rhomberg Rail Australia engaged Amharc to carry out placement of 10.4km of underground track slab as well as the maintenance access platform as part of the massive Cross River Rail project in Brisbane. This involved the casting of the LVT track and blocks along with v-drains either side of the track within the tunnel drive. Amharc were engaged early by Rhomberg to aid in developing and testing proposed methodologies to eliminate time taken to ramp up to full production within the tunnel.


CASE STUDY 15:

Strathpine Intersection Upgrade

Fulton Hogan engaged Amharc to complete 1700m2 of Decorative stencilled concrete slab on island and median infills as part of the upgrade to the Strathpine Road Interchange at Strathpine. This work was carried out on nightshifts to a tight schedule and the highest standard.


Contact Amharc for a no obligation quote.

Need a Quote?

Contact Us at 1300 AMHARC

Scroll to top